Information

Alloy power cabinet maintenance action
                                                                                 --TPM special activity of alloy manufacturing department

Equipment power cabinet dust removal and decontamination maintenance, is the annual maintenance of routine maintenance, daily attention is less, it is easy to ignore the problem, over time, the work of the power cabinet will appear more or less problems, and eventually cause fire, resulting in immeasurable consequences.

 

Themed sessions

      This month for the company's TPM "electronic control cabinet dust removal" theme activities, alloy manufacturing department on August 25, by the department manager Qiao Longtao organized the alloy manufacturing department "electronic control cabinet and equipment control cabinet cleaning and maintenance seminar", the meeting to clarify the maintenance action distribution plan.

Mobilize advocacy

On August 28, the machining team organized 10 people to maintain 24 power cabinets on the site. Before the operation began,Li Pengpeng, the electrician of the equipment department, and Wei Aiguo, the maintenance team leader, explained in detail the precautions required for the operation process.

Check the power supply

After the operation began, the electrician of the equipment department turned off the power supply at the upper level of the power cabinet in the distribution room. After turning off the power supply, the electrician class inspects the 24 power cabinets one by one, and the maintenance class conducts a second inspection to ensure that there is no electricity.

Division of labor

Machining workers are in groups of every 2 people, and the division of labor is cooperative.

Acceptance one by one

After the maintenance, Niu Yunyao, the promoter of the department, inspected the power cabinet after maintenance one by one to ensure that the maintenance of each dead corner was in place.
    This activity has been strongly supported by the equipment department, roll ring machine plus, top hammer machine plus, mold machine plus 24 power cabinets to get a thorough dust removal and pollution maintenance, to remove hidden dangers of failure, the activity achieved a complete success, to achieve the expected effect.
Photo: Three Departments of Alloy Division Niu Yunyao
Audit: Equipment Department Ma Gaofeng